Temporary vermin-compost unit 150 TPA(ton per annum) (ASSAM CONDITION)





COMPONENTS REQ

1 Sheds

For a vermi-composting unit, whether small or big, this is an essential item and is required for having the vermi beds. They could be of thatched roof supported by bamboo rafters and purlins, wooden trusses and stone pillars. If the size is so chosen as to prevent wetting of beds due to rain on a windy day, they could be open sheds. While designing the sheds adequate room has to be left around the beds for easy movement of the labour attending to the filling and harvesting the beds.

2 Vermi-beds

Normally the beds are 75 cm - 90 cm thick depending on the provision of filter for drainage of excess water. The entire bed area could be above the ground. Care should be taken to make the bed with uniform height over the entire width to the extent possible to avoid low production owing to low bed volumes. The bed width should not be more that 1.5 m to allow easy access to the centre of the bed.

3 Land

 About 0.5-1 acre of land will be needed to set up a vermiculture production cum extension centre. The centre will have at least 8-10 sheds each of about 180-200 sq.ft. It should also have a bore well, and pump set or watering arrangement and other equipments as described in the scheme economics. The land can be taken on lease of at least 10-15 years. Even sub marginal land also will serve the purpose.

4 Buildings

When the activity is taken up on a large scale on commercial lines, considerable amount may have to be spent on buildings to house the office, store the raw material and finished product, provide minimum accommodation to the Manager and workers. The cost of the buildings along with the electrification of these buildings and the vermi-sheds may be included under this item.

5 Seed Stock

This is an important item requiring considerable investment. Though the worms multiply fast to give the required numbers over a period of 6 months to a year, it may not be wise to wait till such a time having invested on the infrastructure heavily. Thus, worms @ 350 worms per m3 of bed space should be adequate to start with and to build up the required population in about two cycles or three without unduly affecting the estimated production.

6 Fencing and Roads/Paths

The site area needs development for construction of structures and development of roads and pathways for easy movement of hand-drawn trolleys/wheel barrows for conveying the raw material and the finished products to and from the vermi-sheds. The entire area has to be fenced to prevent trespass by animals and other unwanted elements. These could be estimated based on the length of the periphery of the farm and the length and type of roads/paths required. The costs on fencing and formation of roads should be kept low as these investments are essential for a production unit, yet would not lead to increase in production.

 7 Water Supply System

As the beds have always to be kept moist with about 50% moisture content, there is need to plan for a water source, lifting mechanism and a system of conveying and applying the water to the vermi-beds. Drippers with round the clock flow arrangement would be quite handy for continuous supply and saving on water. Such a water supply/application system requiring considerable initial investment, however, reduces the operational costs on hand watering and prove economical in the long run. The cost of these items depend on the capacity of the unit and the type of water supply chosen.

8 Machinery

Farm machinery and implements are required for cutting (shredding) the raw material in small pieces, conveying shredded raw material to the vermi-sheds, loading, unloading, collection of compost, loosening of beds for aeration, shifting of the compost before packing and for air drying of the compost, automatic packing and stitching for efficient running of the unit. Costs of providing necessary implements and the machinery have to be included in the project cost.

9 Transport

For any vermi-composting unit transport arrangement is a must. When the source of raw material is away from the production unit, an off-site transport becomes major item of investment. A large sized unit with about 1000 tonnes per annum capacity may require a 3-tonne capacity mini-truck. With small units particularly with the availability of raw material near the site, expending on transport facility may become infructuous. On-site transport facilities like manually drawn trolleys to convey raw material and finished products between the storage point and the vermi-compost sheds could also be included in the project cost.

10 Furniture

A reasonable amount could also be considered for furnishing the office-cum-stores including the storage racks and other office equipment. These enhance the efficiency of operations.

11 Operational Costs

In order to operate the unit, expenditure on some items have to be incurred on a recurring basis. These items include salaries of the staff, wages to the labourers, cost of raw material, fuel cost on transport of raw materials and finished goods, packing material cost, repairs and maintenance, power, insurance, etc. The number of office personnel and labourers have to be decided breaking each activity into a number of sub-activities and for each sub-activity estimating the work involved and the capacity of the labour to finish the work in a given time. The number of persons should be so chosen to keep them engaged throughout by providing enough persons at various work points like stores, vermi-beds and equipping them with adequate number of implements to avoid undue waiting.





Annexure-1

Estimate for construction of temporary shed for setting up 150 TPA vermicompost unit

(Size 8 m x 15m x 5.4 m)

Sl.No.
Iteam
Quantity
Rate (Rs.)
Amount (Rs.)
1
Wooden ballies (3 m long)
472
25
7800
2
Wooden ballies (3.6 m long)
48
30
1440
3
Bamboos (3 m long)
800
15
12000
4
Bamboos (6 m long)
240
20
4800
5
Bamboo mats for covering the roof
720
25
18000
6
Coir rope 6 mm dia
200 kg
15
3000
7
Binding wire for tying bamboos & mats
100 kg
25
2500
8
Labour charges for erection of sheds
         -

20000
9
Miscellaneous


2460

Total


72000

Annexure-II
150TPA vermi-compost unit - Implements and machinery

Sl.No.
Particulars of item
Amount (Rs.)
1
Shovels, spades, crowbars, iron baskets,
2800

dung fork, buckets, bamboo baskets,


trowel, wire mesh sieves (3 mm and 6 mm)

2
Plumbing and fitting tools
1000
3
Power operated shredder
20000
4
Sieving maching with 3 wire mesh sieves
35000

0.6 m x 0.9 m size - power operated with out motor

5
Weighing scale (100 kg capacity)
1500
6
Weighing machine (platform type)
5000
7
Bag closer
3000
8
Empty barrels (200 L capacity) 4 Nos.
1600
9
Culture trays (plastic) (35 cmx 45 cm) - 4 Nos
200
10
Wheel barrows - 2 Nos.
10000

Total
80100


Say 80000
Annexure-III
Total operational cost for one cycle of 75 days
Bed volume 330 m3 Recovery percent: 30%

Sl.No.
Particulars
Unit
Rate
Amount (Rs.)
1
Agricultural waster @ 320 kg per m3
105.6 ton
100
10560
2
Cow dung @ 80 kg/m3
26.4 ton
150
3960
3
Worms @ 350 per m3 500 worms per kg
231 kg
50
11550
4
Formation of vermibed with agro-waste, cow dung and worms
330 m3
46
15180
5
Harvesting, sieving, packing, etc., including cost of bags
40 ton
0.45
18000
6
Electrical charges for pump, machinery, lighting etc.
-
-
4800
7
Repair and maintenance
-
-
7950

Total


72000

Cost for 5 cycles


360000

Rent on lease @Rs 8000/year


8000

Total operating cost


368000

Annexure-IV
150 TPA vermi-composting unit - Costs and Benefits


Years


I
II onwards
1
Costs


a)
Investment costs


i)
Open sheds with bamboo mat roofing
72000
-

over bamboo frame work supported



by wooden ballies


ii)
Machinery and tools
80000
-
iii)
Office-cum-store
60000
-
iv)
Water source
60000

v)
2 NADEP tanks
5000


Total
277000

b)
Operational cost
360000
360000

For 5 cycles in a year @ Rs. 72,000 per cycle of 75 days



Lease rent
8000
8000

Total
368000
368000
2
Benefits


a)
Sale of vermicompost of 200 tonnes
300000
450000

@ Rs.2500/- per ton (60% in first year and 90% from 2nd year onwards)


b)
Sale of worms @ 5 kg per tonne of compost and Rs. 50 per kg
-
45000
c)
Consultancy & ext. services
-
10000

Total
300000
505000

Net Benefit
79200*
137000

Operational cost for two cycles is capitalized in the first year

Annexure-V
150 TPA vermicomposting unit - Financial Analysis


(Rs. in lakhs)

Particulars
Years


I
II to IX
1
COSTS


A
Capital Cost


i)
Buildings
1.32
-
ii)
Machinery / tools
0.8
-
iii)
Water supply system
0.6
-
iv)
NADEP tanks
0.05
-
B
Operational cost
3.68
3.68

Total Cost
6.45
3.68
2
BENEFITS


i)
Sale of vermicompost
3.00
4.50
ii)
Sale of worms

0.45
iii)
Consultancy and extension services

0.10

Total benefit
3.000
5.05
3
Net benefit
*0.792
1.37

Discounting Rate 15%



NPV
2.35


IRR
36%


NPV of benefits
22.31


NPV of costs
19.97


BCR
1.12












Annexure-VI
Repayment schedule
Outlay- Rs.4.242 lakh*
Bank loan -Rs. 3.394 lakh
Interest (%)- 15




Repayment


Year
Loan Outstanding
Net Income
Principal
Interest
Total outgoing
Net Surplus







1
339400
79200
 -
50910
50910
28290
2
339400
137000
31000
50910
81910
55090

3
308400
137000
36000
46260
82260
54740

4
272400
137000
41000
40860
81860
55140

5
231400
137000
47000
34710
81710
55290

6
184400
137000
54000
27660
81660
55340

7
130400
137000
62000
19560
81560
55440

8
68400
137000
68400
9510
77910
59090


* including capitalization of operational cost for 2 cycles (Rs.1,47,200/-)


Comments

Popular posts from this blog

Factors Affecting Respiration

Human resources development, Selection and recruitment

E-Arik