Temporary vermin-compost
unit 150 TPA(ton per annum) (ASSAM CONDITION)
COMPONENTS
REQ
1
Sheds
For
a vermi-composting unit, whether small or big, this is an essential item and is
required for having the vermi beds. They could be of thatched roof supported by
bamboo rafters and purlins, wooden trusses and stone pillars. If the size is so
chosen as to prevent wetting of beds due to rain on a windy day, they could be
open sheds. While designing the sheds adequate room has to be left around the
beds for easy movement of the labour attending to the filling and harvesting
the beds.
2
Vermi-beds
Normally
the beds are 75 cm - 90 cm thick depending on the provision of filter for
drainage of excess water. The entire bed area could be above the ground. Care
should be taken to make the bed with uniform height over the entire width to
the extent possible to avoid low production owing to low bed volumes. The bed
width should not be more that 1.5 m to allow easy access to the centre of the
bed.
3
Land
About
0.5-1 acre of land will be needed to set up a vermiculture production cum
extension centre. The centre will have at least 8-10 sheds each of about
180-200 sq.ft. It should also have a bore well, and pump set or watering
arrangement and other equipments as described in the scheme economics. The land
can be taken on lease of at least 10-15 years. Even sub marginal land also will
serve the purpose.
4
Buildings
When
the activity is taken up on a large scale on commercial lines, considerable
amount may have to be spent on buildings to house the office, store the raw
material and finished product, provide minimum accommodation to the Manager and
workers. The cost of the buildings along with the electrification of these buildings
and the vermi-sheds may be included under this item.
5
Seed Stock
This
is an important item requiring considerable investment. Though the worms
multiply fast to give the required numbers over a period of 6 months to a year,
it may not be wise to wait till such a time having invested on the
infrastructure heavily. Thus, worms @ 350 worms per m3 of bed space should be
adequate to start with and to build up the required population in about two
cycles or three without unduly affecting the estimated production.
6
Fencing and Roads/Paths
The
site area needs development for construction of structures and development of
roads and pathways for easy movement of hand-drawn trolleys/wheel barrows for
conveying the raw material and the finished products to and from the
vermi-sheds. The entire area has to be fenced to prevent trespass by animals
and other unwanted elements. These could be estimated based on the length of
the periphery of the farm and the length and type of roads/paths required. The
costs on fencing and formation of roads should be kept low as these investments
are essential for a production unit, yet would not lead to increase in
production.
7
Water Supply System
As
the beds have always to be kept moist with about 50% moisture content, there is
need to plan for a water source, lifting mechanism and a system of conveying
and applying the water to the vermi-beds. Drippers with round the clock flow
arrangement would be quite handy for continuous supply and saving on water.
Such a water supply/application system requiring considerable initial
investment, however, reduces the operational costs on hand watering and prove
economical in the long run. The cost of these items depend on the capacity of
the unit and the type of water supply chosen.
8
Machinery
Farm
machinery and implements are required for cutting (shredding) the raw material
in small pieces, conveying shredded raw material to the vermi-sheds, loading,
unloading, collection of compost, loosening of beds for aeration, shifting of
the compost before packing and for air drying of the compost, automatic packing
and stitching for efficient running of the unit. Costs of providing necessary
implements and the machinery have to be included in the project cost.
9
Transport
For
any vermi-composting unit transport arrangement is a must. When the source of
raw material is away from the production unit, an off-site transport becomes
major item of investment. A large sized unit with about 1000 tonnes per annum
capacity may require a 3-tonne capacity mini-truck. With small units
particularly with the availability of raw material near the site, expending on
transport facility may become infructuous. On-site transport facilities like
manually drawn trolleys to convey raw material and finished products between the
storage point and the vermi-compost sheds could also be included in the project
cost.
10
Furniture
A
reasonable amount could also be considered for furnishing the office-cum-stores
including the storage racks and other office equipment. These enhance the
efficiency of operations.
11
Operational Costs
In
order to operate the unit, expenditure on some items have to be incurred on a
recurring basis. These items include salaries of the staff, wages to the
labourers, cost of raw material, fuel cost on transport of raw materials and
finished goods, packing material cost, repairs and maintenance, power,
insurance, etc. The number of office personnel and labourers have to be decided
breaking each activity into a number of sub-activities and for each sub-activity
estimating the work involved and the capacity of the labour to finish the work
in a given time. The number of persons should be so chosen to keep them engaged
throughout by providing enough persons at various work points like stores,
vermi-beds and equipping them with adequate number of implements to avoid undue
waiting.
Annexure-1
Estimate
for construction of temporary shed for setting up 150 TPA vermicompost unit
(Size
8 m x 15m x 5.4 m)
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Annexure-III
Total
operational cost for one cycle of 75 days
Bed volume 330 m3
Recovery percent: 30%
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Annexure-IV
150
TPA vermi-composting unit - Costs and Benefits
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operational cost for
two cycles is capitalized in the first year
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Annexure-V
150
TPA vermicomposting unit - Financial Analysis
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Annexure-VI
Repayment
schedule
Outlay- Rs.4.242 lakh*
Bank loan -Rs. 3.394
lakh
Interest (%)- 15
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
* including
capitalization of operational cost for 2 cycles (Rs.1,47,200/-)
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Comments